                  Abstract

                         This Research is implemented by applying public participation spectrum for identifying
                  status of People Participatory in Environmental Impact Monitoring for Developing Projects. Research
                  began by reviewing secondary data of environmental quality monitoring and environmental impact
                  preventing measurement implementation report of Bangpakong Combined Cycle Power Plant number

                  5 in operating period. Collecting primary data of peoples living in communities around 5 kilometers
                  from Combined Cycle Power Plant and depth interviewing with sample of communities being
                  researched
                         The result is found that Bangpakong Combined Cycle Power Plant number 5 operates
                  for 10 environmental impact preventing measurements and 6 environmental impact monitoring
                  measurements.  People  participatory  status  in  environmental  impact  preventing  and  monitoring

                  measurements are 10 measurements those are operated in level 1 - 4 of public participation
                  spectrum. Evaluating People participatory status by collecting data from questionnaire for sample
                  peoples,  the  result  found  that  project  operated  People  participatory  for  environmental  impact
                  preventing measurement within level 1 by 52.76%, operating activities of people participatory is

                  in  level  3  by  54.29%.  Project  operates  people  participatory  in  environmental  monitoring
                  measurement within level 1 by 48.67%, operating activities of people participatory is in level 2
                  by 48.67%. In depth interviewing with representatives of 2 communities, they showed opinion that
                  measurements for preventing solving and monitoring environmental impact of project are operated
                  efficiently without any damage impact and people participatory measurement of project is operated
                  frankly and clear by good collaborating of peoples. However, samples also show opinion that project

                  would rather focus on public relation that is not real responsibility than prevent possible impact.
                  For  the  suggestion  to  project,  there  should  be  people  participation  for  impact  monitoring
                  implementing transparently and developing to be more forceful instead of focusing on public relation
                  activity. Besides, project must run impact problems solving by technology energy how when and
                  where for more effectiveness.

                  Keywords: People participation, Environmental impact monitoring, Developing Project